Building stages inspections

Construction Stage Inspection Types and Check lists

1. Pre-slab Stage Inspection

When we inspect:  Prior to pour concrete.

What we inspect:

  • Footing size and slab thickness in accordance with the structural engineer’s plan
  • Steel mesh and Reinforcing bar size, and location with the Structural engineer’s plan
  • Vapour barrier placed and in good condition
  • Completed work is in accordance with the building plans and Australian Standards
  • Installation and location of plumbing and service in the slab
  • Termite protection for plumbing and service penetration

 

2. Wall and Roof Framing Stage Inspection

When we inspect:  Wall framing and roof framing are complete

What we inspect:

  • Wall and roof framing in accordance with the engineer’s plan
  • Steel beam and post schedule and installation
  • Roof and wall framing connections
  • Wall and roof bracing in accordance with the Australian Standard
  • Tie down straps and anchored correctly
  • Windows and doors location
  • Concrete slab finish and any signs of cracking
  • Completed work in accordance with the building plan and BCA

 

3. Pre-Lining/Lock-up Stage Inspection

When we inspect:  When the external wall and roof cladding are completed, and plumbing and service pipes been installed.  Prior the install internal wall lining.

What we inspect:

  • Roof cladding is correctly installed
  • Brickwork is correctly installed
  • Installation and location of plumbing pipes
  • Installation of electrical cables
  • Room and ceiling height
  • Re-inspect wall and roof frames, and are ready for covering
  • Re-inspect all major structural components and are ready for covering
  • Location and installation condition of windows

 

4. Waterproofing Inspection

When we inspect: After completion of waterproofing in the wet areas and prior to install tiles

What we inspect:

  • Check application of waterproofing in accordance with the Australian Standard
  • Installation water stoper and sealing around doorway and shower area

 

5. Practical Completion/Pre-Handover Inspection

When we inspect:  All building activities been completed and ready to move in

What we inspect:

  • Detailed review of all internal finished materials and workmanship in accordance with the al relevant Australian Standards
  • Detailed review of all external finished materials and workmanship in accordance with the all relevant Australian Standards
  • Articulation joints installed to brickwork in accordance with engineer’s plan
  • Check Installation of windows and doors
  • Inspect all trades works and finished components have been completed in accordance the scope of works as contracted
  • External/internal balustrades and handrails in accordance with BCA
  • All elevations that are accordance with the architectural plans
  • Check all appliances installation and specification against plans and contract
  • Bathroom plumbing and fittings installed, and working properly
  • Lights are installed as per plan and working properly
  • Smoke alarms installed
  • Roof plumbing completed and properly connected
  • Install and connection of Air conditioning system
  • Site grading & perimeter drainage completed and adequate
  • Termite installation and durable notice placed
  • Any specific concerns can be reviewed and checked